Construction Alerts

◄ Back
August 30, 2019 10:55 AM

CONSTRUCTION NOTIFICATION Week of SEPTEMBER 16, 2019

PAVING
Monday: Structures and casting pickup
Tuesday: Paving crew on Sheridan St, Boheim and Custer St
Tuesday: Structure Adjustments on Ferry St.

SEWER PROJECTS:
NWM
Clean and CCTV of Railroad Street easement, Merrimack Street, Cross, Cornish Street Easement, Lawrence Street, Short Street, Webster Ct, Riverside Dr
en
P. Gioioso & Sons, Inc.
1st Crew: Orchard Street alley (between Orchard and Summer Street) and Newbury Street alley open cut.

WATER PROJECTS
Market Street: DeFelice will finish work at the intersection of Market St and Osgood St and install trench pavement.

Jackson Street: DeFelice will continue to make water service connections to the newly installed water main on Jackson Street. Affected customers will be given 24 hours’ notice prior to water service connection work; sensitive customers will be given 48 hours’ notice.

Sherman Street and Wilbur Street: DeFelice will continue installation of temporary bypass piping. Bypass piping will be flushed, chlorinated, and tested. If passing sample results are obtained, DeFelice will begin connections to the temporary bypass piping.

MARSTON STREET PROJECT
Pave Surface Course Entire Project ‐ Brox
Apply Temp. Tape Pavement Markings
Pavement Markings ‐ Layout, Recessed Grinding & Markings

Facebook Twitter Email