CONSTRUCTION NOTIFICATION Week of NOVEMBER 18, 2019

PAVING

SEWER PROJECTS

P. Gioioso & Sons, Inc. – Finish up closing Florence/Irene St access pits
Lexington Street slip lining and manhole work

SSES Program (Truax CCTV)

Completed last week: 0
Completed year to date: CCTV of 104,000 LF

Upcoming work:
11/18 – 11/22:

Truax is returning this week for additional CCTV inspections in South Lawrence.


WATER PROJECTS
DWSRF 3814 Contract 2 Water Main Replacement Project:

Anticipated work for the week of November 18, 2019:

No major work planned. Potential punch list work.

Anticipated work for the week of November 25, 2019:

No major work planned. Potential punch list work.

DWSRF 4562 – South Lawrence Valves Assessment and Replacement

Anticipated work for the week of November 18, 2019:

Contract 6981 Emergency Valve Replacement Project: No work planned.

Anticipated work for the week of November 25, 2019:

Contract 6981 Emergency Valve Replacement Project: No work planned.

DWSRF 4594, Contract 6979 South Lawrence Water Main Replacement Project:

Anticipated work for the week of November 18, 2019:

Andover Street: DeFelice will continue to make water service connections to the 16-inch water main in Andover Street. DeFelice plans to detour portions of Andover Street starting Monday (11/18/19) and mobilize a second service crew to expedite water service connections to the 16-inch water main in Andover Street starting Wednesday (11/20/19). Affected customers will be given 24 hours’ notice prior to water service connection work; sensitive customers will be given 48 hours’ notice.

Anticipated work for the week of November 25, 2019:

Andover Street: DeFelice will continue to make water service connections to the 16-inch water main in Andover Street. Affected customers will be given 24 hours’ notice prior to water service connection work; sensitive customers will be given 48 hours’ notice.