November 6, 2020 10:46 AM
CONSTRUCTION NOTIFICATION Week of NOVEMBER 09, 2020
PAVING
Monday October 05 paving on the Tower Hill area starting on:
o Fulton St. from East Haverhill to Prospect St
o Lebanon St. from Hampshire St. to Lawrence St.
o Cross St from Broadway St to Manchester St.
o Pleasant St. from Woodland St to Manchester St.
o Webster Court from Prospect Street to end
WATER WORK
South Lawrence Water Main Design (DWSRF 4594, City Contract 6980)
Furber Street
• Replace remaining water services and connect to new main
South Lawrence Water Main Design (DWSRF 4594, City Contract 6979)
• Fallon Street at Belknap Street intersection replacement - Night work/shutdowns required; Planned for night of 11/9/2020
• Coolidge Street at Belknap Street intersection replacement - Night work/shutdowns required; Planned for night of 11/10/2020
• Andover Street full width paving and casting repairs (11/9-10/2020 – South Broadway to about Gardner Terrace)
South Lawrence Valve Replacement (DWSRF 4562, City Contract 6981) – Night work/shutdowns required
Replace V1020 – South Broadway at Sylvester Street - Night work/shutdowns required; Planned for night of 11/8/2020
Planned work the week of November 15, 2020
South Lawrence Water Main Design (DWSRF 4594, City Contract 6980)
Furber Street
• Replace remaining water services and connect to new main
Remove temporary bypass in Everett Street and Furber Street
SEWER WORK
Cutting laterals on
• Hampshire Street
• Irene Street
• Tudor Avenue
• Smith Street
• Winter Street
• Gale Street
• Fordham Road
• School Street
CCTV on
• Oxford St
• Margin St